Case Study Of Aldborough School

Location – Redbridge, Greater London

Project – The project entailed to construct a two storey Kitchen & 1st Floor Class base extension within the schools existing playground area. Specifically these works involved the following:-

  • Installation of new mains gas, water and electrical services
  • Structural and roofing alterations to existing lift motor room
  • Excavation of existing playground area
  • Construction of a new build Kitchen & 1st Floor Class base extension
  • Installation of new playground astro turf/playing surface
  • Overall project duration  – 43 weeks
  • Original programme duration  – 18 weeks – for a ground floor kitchen extension only
  • Extension of time granted – 25 weeks – due to the additional works instruction of a first floor classbase and planning permission acceptance/approval 
  • Original project works cost total - £279,371.25 nett
  • Agreed project final account cost total - £474,898.60 nett – due to additional works instructions