Case Study Of Hurstmere School

Location – Sidcup, Kent

  • Project – The works include hot water, cold water and boiler replacement works. Specifically these work involved the following:-
  • Installation of new hot and cold water pipework
  • Replacement of water tanks, boilers and all associated equipment
  • Alterations and refurbishment of the boiler room
  • New external gas and water service pipework run below ground in shared access drive
  • Associated builders work and making good
  • Asbestos removal works
  • Overall project duration – 19 weeks
  • Original programme duration – 14 weeks 
  • Extension of time granted – 4 weeks – due to the additional client works instructions
  • Original project works cost total – £575,733.00 nett
  • Agreed project final account cost total – £663,488.87 nett – due to additional client works instructions